The Kali Gandaki-A is on line. The 144 mW project began by supplying 48 megawatts of electricity to the central grid on 24 February, almost a year after the originally anticipated completion date, and a month after it began trial runs. Its two other 48 mW generators are waiting to begin generating power pending completion of transmission lines to Pokhara. Construction on Kali Gandaki-A began in 1996.